Most people ask how long the builders will be on site, but the build is only part of the timeline. From the first conversation to moving into the new room, a house extension in Derby usually takes somewhere between four and nine months, and the stages before anyone picks up a spade often take longer than the build itself. Here is how the time breaks down, and what you can do to keep it moving.
The short answer
As a guide, once work starts on site:
- A kitchen extension takes around 8 to 12 weeks
- A single-storey rear or side extension takes around 10 to 14 weeks
- A two-storey extension takes around 14 to 20 weeks
Before that, allow anything from a few weeks to three or four months for design, approvals and preparation, depending on whether the extension needs planning permission.
Stage 1: design and drawings (2 to 6 weeks)
The first step is agreeing what you want the extension to do: a bigger kitchen, a family room, a ground-floor bedroom, or space upstairs. From a site visit and measured survey, drawings are prepared showing the layout, the elevations and how the extension joins the house. Most of the time here goes on decisions, so knowing roughly how you want to use the space before the first meeting saves weeks.
Stage 2: planning (0 to 12 weeks)
This is the stage that varies most. If the extension falls within permitted development, there is no planning application at all, though many people apply for a Lawful Development Certificate for peace of mind. A larger single-storey rear extension under the prior approval route takes up to 42 days. A full householder planning application has an eight-week target once the council validates it, and amendments or a busy planning department can push that further.
Homes in conservation areas, the Derwent Valley Mills World Heritage Site or listed buildings need more careful design and often more time. Our guide to planning permission for extensions in Derby explains which route applies.
Stage 3: building regulations, structural design and party walls (4 to 8 weeks, alongside planning)
While planning is underway, the structural engineer’s calculations and the building regulations drawings can be prepared, and building control approval sought. If the extension is on or near a shared wall or boundary, party wall notices go to the neighbours. Neighbours have 14 days to respond, and the notice period is one or two months depending on the work, so serving notices early stops them delaying the start.
This is also the time to order anything with a long lead time. Bifold and sliding doors, roof lanterns, made-to-measure windows and kitchens can take six to ten weeks to arrive, and ordering them once the build has started is the most common cause of delays later.
Stage 4: the build (8 to 20 weeks)
On site, a typical single-storey extension runs in this order:
- Groundwork and foundations (1 to 2 weeks). Digging out, inspecting and pouring the foundations, and laying any drainage that needs to move. Building control inspects the foundations before they are filled.
- Walls to roof level (2 to 3 weeks). Blockwork and brickwork, with the cavity insulation and the steel beam that opens the extension into the house.
- Roof and windows (2 to 3 weeks). Once the roof is on and the windows and doors are fitted, the extension is weathertight and the inside work can begin.
- First fix (1 to 2 weeks). Plumbing, heating, electrics and data cables run before the walls are plastered.
- Plastering, screed and drying (2 to 3 weeks). A floor screed needs time to dry before flooring goes down, and this stage cannot be rushed.
- Second fix and finishing (2 to 3 weeks). Kitchen fitting, sockets and lighting, joinery, flooring, tiling and decorating.
- Knock-through and sign-off. The opening into the existing house is often formed late, to keep the house usable for as long as possible, followed by the building control completion inspection.
A two-storey extension adds the first floor, the stair or landing connection and more internal work, which is why it takes longer.
What causes delays
- Weather. Heavy rain or frost can hold up groundwork and brickwork. Projects that start in spring usually get the shell up fastest.
- Surprises underground. Old drains, poor ground or tree roots can mean deeper foundations. A site survey reduces the risk, but nobody can see everything before digging.
- Late decisions. Changing the layout or the kitchen once work has started has a knock-on effect on every trade after it.
- Waiting between trades. When the bricklayer, roofer, plumber, electrician and plasterer are all booked separately, each one waits for the last. This is one of the biggest causes of extensions overrunning.
Living at home during the work
Most families stay at home during a single-storey extension. The existing house is kept sealed off from the work for most of the build, and the noisiest, dustiest stages are over within the first few weeks. The hardest stretch is usually the kitchen, if the extension involves replacing it, so we plan a temporary kitchen area and agree the order of work with you before we start.
One team, one programme
Derbyshire Specialists Group builds extensions with its own team covering groundwork, building, roofing, plumbing, electrics, plastering, kitchens, tiling and joinery, all run by one project manager. That means one programme from start to finish and no gaps waiting for the next trade. See our house extensions page for more, or book a free visit on 01332 215256 and we will give you a realistic timescale for your project.